THREE60 Energy managed a complete package of load testing for a client, covering SDA and mudmat units across a range of test configurations.
Delivered from THREE60’s Rosyth facility, the scope included a 63.5-tonne mudmat load test and an SDA horizontal pull test using a 250-tonne test bed.
Challenge
The client required multiple components to be tested across different configurations, creating a need for careful planning, coordination and specialist lifting and testing expertise.
The programme also presented opportunities to improve the proposed testing methodology to reduce execution time and associated costs.
Solution
THREE60 managed the complete testing scope, including crane hire and lift planning, while working with the client to develop the test specification.
The team reviewed the proposed approach and recommended improved testing methods to make the programme more efficient, before coordinating and executing the required load tests at the Rosyth facility.
Result
The testing programme was successfully completed across the required configurations, including the 63.5-tonne mudmat test and horizontal pull testing using THREE60’s 250-tonne test bed.
By managing the complete scope and optimising the testing methodology, THREE60 helped the client reduce testing time and costs, with the team commended for its professional approach throughout the project.